Construction Public Notice

The Aquatic V – 2628 Shattuck Ave..

Project Description: Construction of a 6-story building, consisting of 78 apartment units with commercial spaces and parking below.

Construction Activities: Major phases of construction to include the following -

·         Demo of existing building and site hardscape.

·         Excavation and grading to follow for preparation of building foundation.

·         Underground utilities.  

·         Forming and subsequent pouring of concrete foundation, walls and podium slab to occur.

·         Five stories of vertical framing including exterior and interior building finishes.

·         Site improvements including the landscaping, sidewalks, etc.

·         Daily construction activities one can expect are use of hand tools (hammers, drills, etc.), hauling and hoisting

of material, construction equipment such as bobcats, backhoes, reach lifts running for various activities.   

Anticipated General Schedule:

▪ Demo/Grading (August 2019 – November 2019)

▪ Concrete Construction & Utilities (November ’19 – March ’20)

▪ Framing (March ’20 – October ’20)

▪ Façade and Finishes (October ‘20 – July ’20):

 

Daily Construction Schedule:

·         Work will commence 7am - 6pm Monday through Friday.

·         This project is approved for Saturday work if needed 9am - 4pm.

·         Expected Start: August 2019

·         Expected Duration 22 months.

 

Noise Management Individuals:

·         Miranda Mills: (510) 910-3980 - Construction Noise Liaison

·         Derik DeLonzor: (510) 778-0439

The above are WEST Builders site staff, please feel free to contact with questions or concerns

or via email: Aquatic5@westbuilders.net